Letter of Transmittal
Re: Proposed T-hangar and box hangar development, east hangar area, Wexley Field. Feasibility and demand study.
Dear Commissioners,
At your request we have studied whether the Authority should build the hangars shown for the east hangar area on the airport layout plan: one ten unit T-hangar building and four 60 by 60 foot box hangars. You asked whether there is demand at a rent that pays for the buildings, whether the Authority should build them or lease the ground to others, and what rent the new units should carry.
Our findings are as follows. The box hangars are feasible. At a market rent of $12.00 per square foot per year they return 7.52 percent on a cost of $2,328,704, against the Authority's 6.50 percent hurdle, with a net present value of $363,820. The T-hangar building is not feasible on rent alone. At a market rent of $450 per month it returns 2.08 percent on a cost of $1,687,840, and its net present value is ($917,042). It becomes feasible only if grant funding covers at least 54.3 percent of the cost.
We recommend that the Authority offer the four box hangar sites by ground lease, which is worth $642,337 to the Authority in present value with no capital at risk, and that it build the T-hangars only if grant funding is secured.
This study is a sample. The airport, the parties and every figure in it are illustrative, assembled to show the format and depth of analysis we deliver.
Respectfully submitted,
VALUATION TAKES FLIGHT LLC
Dr. Carter, DBA, CFA, FRM, CAIA, CIPM
Signature omitted. This is a sample study.
1. Summary of Findings
| Item | T-hangar building | Box hangars |
|---|---|---|
| Program | One building, ten nested units, 1,260 SF each | Four units, 60 by 60 feet, 3,600 SF each |
| Building area | 12,600 SF | 14,400 SF |
| Total development cost | $1,687,840 | $2,328,704 |
| Concluded market rent | $450 per unit per month | $12.00 per SF per year, $3,600 per unit per month |
| Qualified demand at that rent | 17 names for 10 units | 7 names for 4 units |
| Stabilized net operating income | $40,880 | $137,445 |
| Return on cost | 2.42 percent | 5.90 percent |
| Internal rate of return, 40 years | 2.08 percent | 7.52 percent |
| Net present value at 6.50 percent | ($917,042) | $363,820 |
| Finding | Not feasible on rent alone | Feasible |
| Recommendation | Build only with grant funding of at least 54.3 percent of cost | Offer the sites by ground lease |
Exhibit 1. Summary of findings. Illustrative figures for a sample airport.
What would change the findings
Each finding holds within limits. The table states the limit for each, so the Board can see how much room it has.
| Finding | It would change if | Where the limit sits |
|---|---|---|
| T-hangars are not feasible on rent alone | Grants pay a large share of cost, or rent rises far above what the survey supports | Grants of 54.3 percent of cost, or a rent of $838 per month against a concluded $450 |
| Box hangars are feasible if the Authority builds | Rent, cost, vacancy or growth moves against the project | Rent below $10.43 per square foot, cost more than 15.1 percent above the estimate, stabilized vacancy above 16.3 percent, or growth below 1.75 percent a year |
| A ground lease is worth more than building | The Authority's cost of funds is low, or the lease term runs long | A discount rate below 5.46 percent, or a term that reaches 40 years |
Exhibit 2. The limits within which each finding holds. Illustrative figures for a sample airport.
2. Scope of the Study
The questions
The study answers the three questions in the letter of transmittal: demand at a rent that covers cost, who should build, and what the new units should rent for. The intended user is the Board, for a decision on the east hangar area in the next capital program.
What we did
We toured the east hangar area and the existing hangars. We read the airport layout plan, the leasing policy, the rents and fees schedule, and the hangar waiting lists. We obtained based aircraft counts for three years from airport management. We surveyed hangar rents, occupancy and waiting lists at the three airports that compete with Wexley Field for based aircraft, and confirmed each rent with the sponsor or the operator. We contacted every name on both waiting lists.
What we did not do
This is a study of demand, rent, and financial return. It is not an engineering or site design product. Construction cost figures were supplied by the Authority's engineer and we did not verify them. We did not study environmental conditions or airspace.
Method
- Demand. We count names on the waiting lists, reach as many as will answer, and ask each one for a commitment at a stated rent. Only names that would sign and place a deposit are counted.
- Rent. We compare rents at the competing airports, adjust them for age and for the airport, and test the result against what the waiting list names said they would pay.
- Return. We project income, expenses and capital renewal for 40 years and discount them at the Authority's 6.50 percent rate. A project is feasible when the present value of its cash flow exceeds its cost.
- Who should build. We value the same sites under a ground lease, where a tenant builds and the hangars pass to the Authority at expiration, and compare the result with building.
Assumptions in one place
| Assumption | T-hangar building | Box hangars |
|---|---|---|
| Units | 10 units of 1,260 square feet | 4 units of 3,600 square feet |
| Market rent | $450 per unit per month | $12.00 per square foot per year |
| Vacancy and collection loss, year 1 | 5 percent | 15 percent |
| Vacancy and collection loss, later years | 3 percent | 3 percent |
| Operating expenses and reserves | $1,150 per unit | 18 percent of effective gross income |
| Growth in rent and expenses | 2.75 percent a year | 2.75 percent a year |
| Capital renewal | 10 percent of building cost in year 20, escalated | 10 percent of building cost in year 20, escalated |
| Building cost | $95 per square foot | $118 per square foot |
| Site work, taxilane, apron and utilities | $310,000 | $380,000 |
| Design, permitting, inspection and contingency | 12 percent | 12 percent |
| Period of analysis | 40 years, with no value at the end | 40 years, with no value at the end |
| Discount rate | 6.50 percent | 6.50 percent |
Exhibit 3. The assumptions behind the financial analysis. Illustrative figures for a sample airport.
3. Wexley Field and the Competing Airports
Wexley Field is a general aviation airport with one 6,000 foot runway, a full parallel taxiway, a precision instrument approach, one fixed base operator, and both jet A and 100LL. It is federally obligated. The Authority owns 84 T-hangar units built between 1998 and 2006 and six box hangars, all occupied. Fourteen private hangars stand on ground leases.
| Based aircraft | Three years ago | Last year | Current |
|---|---|---|---|
| Single engine piston | 112 | 115 | 118 |
| Multi engine piston | 22 | 22 | 21 |
| Turboprop | 15 | 16 | 17 |
| Jet | 18 | 20 | 22 |
| Helicopter | 7 | 7 | 8 |
| Total | 174 | 180 | 186 |
Exhibit 4. Based aircraft at Wexley Field, from airport records. Illustrative figures for a sample airport.
The fleet has grown by twelve aircraft in three years, and six of the twelve are turbine. Piston singles fill T-hangars. Turboprops, light jets and twins fill box hangars. Growth is strongest in the aircraft that need the larger unit.
| Airport | Role | Longest runway | Based aircraft | T-hangar rent per month | Box hangar rent per SF per year | Occupancy | Waiting list |
|---|---|---|---|---|---|---|---|
| Wexley Field, existing units | General aviation reliever | 6,000 ft | 186 | $365 | $9.60 | 100 percent | 46 T-hangar, 31 box |
| Corbin Regional | General aviation | 5,400 ft | 152 | $395 | $10.20 | 100 percent | 14 names |
| Halverson Executive | Corporate emphasis | 7,100 ft | 171 | $520 | $14.40 | 100 percent | 44 names |
| Delmar Municipal | Basic general aviation | 4,300 ft | 88 | $290 | $7.20 | 91 percent | None |
Exhibit 5. Competing airports, hangar rent and occupancy. Illustrative figures for a sample airport.
Three of the four fields are full. Two box hangars totaling 30,000 square feet are under construction at Halverson. Nothing is under construction at Wexley Field or Corbin.
Where the fleet is stored
| Storage | Supply | Based aircraft |
|---|---|---|
| Authority T-hangars | 84 units | 84 |
| Authority box hangars | 6 units | 9 |
| Private hangars on ground leases | 14 hangars | 24 |
| Community hangar of the fixed base operator | 24,000 square feet | 14 |
| Tiedowns | Assigned by the month | 55 |
| Total | 186 |
Exhibit 6. Where the 186 based aircraft are stored, from airport records. Illustrative figures for a sample airport.
Fifty-five aircraft sit outside on tiedowns. They are the first source of demand for a new hangar, and the waiting lists also carry owners based at other airports.
Fleet growth by class
The based fleet grew from 174 to 186 in three years, 2.2 percent a year. Turboprops and jets together went from 33 to 39, and piston singles from 112 to 118. Six more turbine aircraft are six more candidates for a box hangar, and none of the Authority's six is vacant.
Supply on the way
The two box hangars under construction at Halverson Executive add 30,000 square feet at an airport that charges $14.40 per square foot, 20 percent above the rent concluded here. They will take some turbine owners who value the longer runway. They do not compete for an owner who wants to stay at Wexley Field at $12.00.
4. Testing the Waiting Lists
A waiting list shows demand at the rent charged today. The Authority's lists were built at $365 per month for a T-hangar and $9.60 per square foot for a box hangar. New buildings cannot be rented at those rates. We therefore asked each name what it would do at the rent a new building needs.
| Waiting list | Names on list | Reached | Would rent at current rate | Would sign at market rent for a new unit | Would sign at a higher test rent |
|---|---|---|---|---|---|
| T-hangar | 46 | 29 | 29 at $365 | 17 at $450 | 6 at $550 |
| Box hangar | 31 | 19 | 19 at $9.60 per SF | 7 at $12.00 per SF | 3 at $14.00 per SF |
Exhibit 7. Waiting list survey. Each respondent was asked whether it would sign a twelve month agreement and place a deposit at the stated rent. Illustrative figures for a sample airport.
Seventeen names would take a new T-hangar at $450, which covers the ten proposed units 1.7 times. Seven would take a box hangar at $12.00 per square foot, which covers the four proposed units 1.75 times. Seventeen of the T-hangar names and twelve of the box hangar names could not be reached, and we give them no weight.
On the raw lists the Authority has 77 names for 14 units. At the rent the new buildings need, it has 24. That is enough to fill both buildings, and it is the figure a lender or grant reviewer will rely on.

The rent that fills the buildings
The survey gives three points on each demand curve. Read on a straight line between the last two, ten T-hangar units fill at about $514 per month and four box hangars fill at about $13.50 per square foot. Both are above the rents we conclude in Section 5. We hold to $450 and $12.00 because each leaves its building covered about 1.7 times, and a study should not rest on the last name on the list.
The higher rents would not change the T-hangar finding. At $514 the net present value is ($766,747). At $13.50 the box hangars would be worth $710,756.
From names to signed agreements
A name that says it would sign is not a signed agreement. The table shows how many units fill if only a share of the names follow through.
| Share of names that sign | T-hangar names that sign | Ten units fill | Box hangar names that sign | Four units fill |
|---|---|---|---|---|
| 100 percent | 17 | Yes | 7 | Yes |
| 75 percent | 12 | Yes | 5 | Yes |
| 60 percent | 10 | Yes | 4 | Yes |
| 50 percent | 8 | No | 3 | No |
Exhibit 9. Units filled if only a share of the names that said they would sign do so. Illustrative figures for a sample airport.
The T-hangar building fills if 59 percent of the 17 names sign, and the box hangars fill if 57 percent of the 7 do. Before a construction contract is awarded, the Authority should hold signed agreements with deposits for at least seven of the ten T-hangar units and three of the four box hangars.
Where the demand comes from
| Names that would sign at market rent | T-hangar | Box hangar |
|---|---|---|
| Aircraft on a Wexley Field tiedown | 11 | 1 |
| Aircraft in the community hangar | 0 | 2 |
| Aircraft based at another airport | 4 | 3 |
| Buying an aircraft | 2 | 1 |
| Total | 17 | 7 |
Exhibit 10. Where the names that would sign keep their aircraft today. Illustrative figures for a sample airport.
T-hangar demand is mostly local: 11 of the 17 names already pay the Authority for a tiedown. Box hangar demand is mostly new to the Authority's rent roll. Section 8 counts what that difference is worth.
5. Market Rent for the New Units
New units rent above units that are twenty years old, and the evidence brackets the premium. The existing T-hangars rent at $365 and Halverson, a stronger field, rents at $520. The survey in Section 4 shows demand holding at $450 and thinning at $550. We conclude a market rent of $450 per month for a new T-hangar unit.
For box hangars the existing units rent at $9.60 per square foot and Halverson at $14.40. Demand holds at $12.00 and thins at $14.00. We conclude $12.00 per square foot per year, which is $3,600 per month for a 3,600 square foot unit, with the Authority paying building insurance, structural maintenance and common area costs.
Both rents are within what FAA Order 5190.6C, paragraph 17.9, allows for aeronautical hangars, where rent may be set at fair market value. Grant Assurance 24 asks for a fee and rental structure that makes the airport as self-sustaining as possible.
Adjustment of the comparable rents
The table adjusts each comparable rent to a new unit at Wexley Field. The first adjustment is for age and condition. The second is for the airport: runway, services and the depth of its market.
| Comparable | T-hangar rent per month | Box rent per square foot | Age and condition | Airport | T-hangar, adjusted | Box, adjusted |
|---|---|---|---|---|---|---|
| Wexley Field, existing units | $365 | $9.60 | Up 20 percent | None | $438 | $11.52 |
| Corbin Regional | $395 | $10.20 | Up 10 percent | Up 5 percent | $456 | $11.78 |
| Halverson Executive | $520 | $14.40 | Up 5 percent | Down 15 percent | $464 | $12.85 |
| Delmar Municipal | $290 | $7.20 | Up 25 percent | Up 20 percent | $435 | $10.80 |
Exhibit 11. Comparable rents adjusted to a new unit at Wexley Field. Adjustments are applied in sequence. Illustrative figures for a sample airport.
The adjusted T-hangar rents run from $435 to $464 and the adjusted box hangar rents from $10.80 to $12.85. The concluded rents of $450 and $12.00 sit inside both ranges, and the survey in Section 4 confirms that demand holds at each. In an engagement each adjustment is supported by paired rents, and the support is shown.
Market rent against the rent that pays for the building
| Unit | Market rent | Rent that returns 6.50 percent on cost | Market rent as a share of it |
|---|---|---|---|
| New T-hangar unit, per month | $450 | $838 | 53.7 percent |
| New box hangar, per square foot per year | $12.00 | $10.43 | 115.1 percent |
Exhibit 12. Market rent and the rent that would return the Authority's rate on the cost of each building. Illustrative figures for a sample airport.
The two products sit on opposite sides of cost. A new box hangar rents for more than it costs to provide. A new T-hangar rents for about half. FAA Order 5190.6C, paragraph 17.9, lets a sponsor charge for hangars at a level between cost and fair market value. For the T-hangars that range is empty, because the market will not pay cost. That is the feasibility finding stated as a rent.
6. Development Cost
The Authority's engineer supplied the following cost estimates in current dollars. We use them as given.
T-hangar building
| Cost line | Amount |
|---|---|
| Building, 12,600 SF at $95 per SF | $1,197,000 |
| Site work, taxilane, apron and utilities | $310,000 |
| Design, permitting, inspection and contingency at 12 percent | $180,840 |
| Total development cost | $1,687,840 |
| Cost per unit | $168,784 |
Exhibit 13. T-hangar development cost, from the Authority's engineer. Illustrative figures for a sample airport.
Box hangars
| Cost line | Amount |
|---|---|
| Building, 14,400 SF at $118 per SF | $1,699,200 |
| Site work, taxilane, apron and utilities | $380,000 |
| Design, permitting, inspection and contingency at 12 percent | $249,504 |
| Total development cost | $2,328,704 |
| Cost per square foot of building | $162 |
Exhibit 14. Box hangar development cost, from the Authority's engineer. Illustrative figures for a sample airport.
What the estimate covers
| Item | Treatment |
|---|---|
| Buildings, doors, slab and electrical service | Included, at $95 and $118 per square foot |
| Taxilane, apron, drainage and utilities to the buildings | Included as site work |
| Design, permitting, inspection and contingency | Included at 12 percent |
| Land | Owned by the Authority. No cost is charged |
| Interest during construction and financing costs | Not included |
| Off-site utility extensions and environmental work | Not included. None was identified to us |
Exhibit 15. What the engineer's estimate includes and leaves out. Illustrative figures for a sample airport.
Cost risk
The estimate is in current dollars, and construction cost has been rising. The Turner Building Cost Index rose 8.0 percent in 2022, 6.0 percent in 2023, 3.9 percent in 2024 and 4.1 percent in 2025, as reported in the firm's paper on hangar waiting lists and FAA rate policy. At the 2025 rate, a one year delay adds $95,477 to the box hangars and $69,201 to the T-hangar building.
The box hangars stay feasible until cost runs 15.1 percent over the estimate. Bids should be compared with that margin before a contract is awarded.
7. T-Hangar Financial Feasibility
| Line | Amount |
|---|---|
| Gross potential rent | $54,000 |
| Less vacancy and collection loss at 3 percent | ($1,620) |
| Effective gross income | $52,380 |
| Less operating expenses and reserves, $1,150 per unit | ($11,500) |
| Net operating income, stabilized | $40,880 |
| Total development cost | $1,687,840 |
| Return on cost | 2.42 percent |
Exhibit 16. T-hangar stabilized operating statement, first year dollars. Illustrative figures for a sample airport.
A return on cost of 2.42 percent does not cover the Authority's cost of funds. Over a 40 year building life, with rent and expenses growing 2.75 percent a year and a capital renewal of 10 percent of building cost in year 20, the cash flow is worth $770,798 at 6.50 percent. The building costs $1,687,840. The net present value is ($917,042).
| Year | Effective gross income | Operating expenses | Net operating income | Capital renewal | Cash flow |
|---|---|---|---|---|---|
| 1 | $51,300 | ($11,500) | $39,800 | $0 | $39,800 |
| 2 | $53,820 | ($11,816) | $42,004 | $0 | $42,004 |
| 3 | $55,301 | ($12,141) | $43,159 | $0 | $43,159 |
| 5 | $58,384 | ($12,818) | $45,566 | $0 | $45,566 |
| 10 | $66,865 | ($14,680) | $52,185 | $0 | $52,185 |
| 20 | $87,704 | ($19,255) | $68,449 | ($205,935) | ($137,487) |
| 30 | $115,037 | ($25,256) | $89,781 | $0 | $89,781 |
| 40 | $150,889 | ($33,128) | $117,761 | $0 | $117,761 |
Exhibit 17. T-hangar cash flow, selected years. Illustrative figures for a sample airport.
The rent that would bring the net present value to zero is $838 per month. Six names on the waiting list would pay $550, and the break-even rent is well beyond that. The T-hangars cannot be built on rent alone.
With grant funding
| Share of cost paid by grants | Authority's cost | Net present value to the Authority |
|---|---|---|
| 0 percent | $1,687,840 | ($917,042) |
| 25 percent | $1,265,880 | ($495,082) |
| 50 percent | $843,920 | ($73,122) |
| 75 percent | $421,960 | $348,838 |
| 90 percent | $168,784 | $602,014 |
Exhibit 18. T-hangar net present value by grant share. Illustrative figures for a sample airport.
The building breaks even when grants pay 54.3 percent of the cost. Above that share the T-hangars add value. Grant Assurance 24 excludes the federal share of grant-funded development from the rate base, so a grant-funded building also supports a lower cost-based rent if the Board prefers one.
Where the value falls short
| Period | T-hangars, present value | Share of cost | Box hangars, present value | Share of cost |
|---|---|---|---|---|
| Years 1 to 10 | $327,388 | 19.4 percent | $1,088,174 | 46.7 percent |
| Years 11 to 20 | $171,027 | 10.1 percent | $688,555 | 29.6 percent |
| Years 21 to 30 | $160,343 | 9.5 percent | $539,099 | 23.2 percent |
| Years 31 to 40 | $112,040 | 6.6 percent | $376,696 | 16.2 percent |
| Total | $770,798 | 45.7 percent | $2,692,524 | 115.6 percent |
Exhibit 19. Present value of cash flow by decade, for both buildings, at 6.50 percent. Illustrative figures for a sample airport.

Over 40 years the T-hangar building returns 45.7 percent of its cost in present value. The box hangars return their cost in year 31 and 115.6 percent by year 40. The T-hangars never come close, in any decade.
Funding the gap
The gap is $917,042. Federal law lets a nonprimary airport put its entitlement into a hangar once airside needs are provided for. The entitlement is $150,000 a year and may be banked for up to four years, so about $600,000 is available. Section 10 sets out the rules.
| Funding | Amount | Net present value to the Authority |
|---|---|---|
| Rent alone | $0 | ($917,042) |
| Banked nonprimary entitlement | $600,000, 35.5 percent of cost | ($317,042) |
| Entitlement and a further grant | $917,042 in grants, 54.3 percent of cost | $0 |
| Interest free loan for 80 percent of cost, repaid over 20 years, and no grant | $1,350,272 loan | ($310,669) |
| Entitlement, and an interest free loan for 80 percent of the balance | $600,000 grant and $870,272 loan | $73,775 |
Exhibit 21. T-hangar net present value under five ways of funding the building. Illustrative figures for a sample airport.
The entitlement alone leaves a gap of $317,042. With it, the rent that breaks even is $584 per month, and only six names would pay $550. A second source closes the gap. At the Authority's rate an interest free loan is worth 44.9 cents for every dollar borrowed, because the Authority repays in later dollars without interest. Minnesota offers state system airports an 80 percent interest free hangar loan repaid over 20 years, described in the firm's paper on federal hangar funding. If the Authority's state offers a program of that kind, entitlement and loan together bring the T-hangars to a positive result of $73,775.
8. Box Hangar Financial Feasibility
| Line | Amount |
|---|---|
| Gross potential rent | $172,800 |
| Less vacancy and collection loss at 3 percent | ($5,184) |
| Effective gross income | $167,616 |
| Less operating expenses and reserves at 18 percent | ($30,171) |
| Net operating income, stabilized | $137,445 |
| Total development cost | $2,328,704 |
| Return on cost | 5.90 percent |
Exhibit 22. Box hangar stabilized operating statement, first year dollars. Illustrative figures for a sample airport.
We assume three of the four units are leased at opening and the fourth within the first year, which is a 15 percent vacancy in year 1 and 3 percent after. On the same 40 year basis the cash flow is worth $2,692,524 against a cost of $2,328,704. The net present value is $363,820 and the internal rate of return is 7.52 percent.
| Year | Effective gross income | Operating expenses | Net operating income | Capital renewal | Cash flow |
|---|---|---|---|---|---|
| 1 | $146,880 | ($26,438) | $120,442 | $0 | $120,442 |
| 2 | $172,225 | ($31,001) | $141,225 | $0 | $141,225 |
| 3 | $176,962 | ($31,853) | $145,109 | $0 | $145,109 |
| 5 | $186,828 | ($33,629) | $153,199 | $0 | $153,199 |
| 10 | $213,970 | ($38,515) | $175,455 | $0 | $175,455 |
| 20 | $280,653 | ($50,518) | $230,136 | ($292,335) | ($62,199) |
| 30 | $368,119 | ($66,261) | $301,858 | $0 | $301,858 |
| 40 | $482,844 | ($86,912) | $395,932 | $0 | $395,932 |
Exhibit 23. Box hangar cash flow, selected years. Illustrative figures for a sample airport.
Sensitivity to rent and cost
| Net present value | Cost 10 percent lower | Cost as estimated | Cost 10 percent higher |
|---|---|---|---|
| Rent 10 percent lower | $327,438 | $86,271 | ($154,895) |
| Rent as concluded | $604,986 | $363,820 | $122,654 |
| Rent 10 percent higher | $882,535 | $641,369 | $400,202 |
Exhibit 24. Box hangar net present value under rent and cost changes. Illustrative figures for a sample airport.
The project stays positive in eight of the nine cases. It turns negative only when rent comes in 10 percent low and cost comes in 10 percent high together. The margin is positive but narrow.
Break-even points
| Input | As concluded | Value at which the net present value is zero |
|---|---|---|
| Market rent per square foot | $12.00 | $10.43 |
| Development cost | $2,328,704 | $2,680,008, 15.1 percent above the estimate |
| Vacancy and collection loss after year 1 | 3 percent | 16.3 percent |
| Growth in rent and expenses | 2.75 percent | 1.75 percent |
| Discount rate | 6.50 percent | 7.52 percent, the internal rate of return |
Exhibit 25. Box hangar break-even points, each input moved alone. Illustrative figures for a sample airport.
Rent can fall 13.1 percent, or cost can rise 15.1 percent, before the project stops paying. Growth leaves less room than the others: the project needs rent to rise at least 1.75 percent a year for 40 years.
If the Authority borrows
A positive net present value over 40 years does not mean the project pays its own debt from the first year. The table tests level debt for the full cost at 5.00 percent, an assumed rate.
| Loan term | Annual debt service | Coverage in year 2 | Coverage in year 10 | Coverage reaches 1.00 | Coverage reaches 1.25 |
|---|---|---|---|---|---|
| 20 years | $186,861 | 0.76 | 0.94 | Year 13 | Not within the loan |
| 25 years | $165,227 | 0.85 | 1.06 | Year 8 | Year 17 |
| 30 years | $151,486 | 0.93 | 1.16 | Year 5 | Year 13 |
Exhibit 26. Debt service coverage if the Authority borrows the full cost of the box hangars at 5.00 percent. Illustrative figures for a sample airport.
On a 25 year loan the box hangars cover 85 percent of their debt service in year 2 and do not cover it in full until year 8. The Authority would carry the shortfall from other revenue for seven years. The project is feasible on value and is not self-supporting on debt in its first years, which is one more reason to look at the ground lease.
Simulation
We drew 10,000 cases in which four inputs vary together: cost around the estimate with a standard deviation of 8 percent, market rent with a standard deviation of 7 percent, growth around 2.75 percent with a standard deviation of 0.75 points, and vacancy between 1 and 5 percent. The ranges are assumptions.
| Result of 10,000 cases | T-hangars, Authority builds | Box hangars, Authority builds | Box hangar sites, ground lease |
|---|---|---|---|
| Mean net present value | ($912,340) | $381,917 | $653,922 |
| 5th percentile | ($1,207,244) | ($273,726) | $473,696 |
| 95th percentile | ($608,970) | $1,087,571 | $882,085 |
| Share of cases with a positive result | 0.0 percent | 82.0 percent | 100.0 percent |
Exhibit 27. Simulation of cost, rent, growth and vacancy. Illustrative figures for a sample airport.

The T-hangars are negative in every case. The box hangars are positive in 82 percent of cases if the Authority builds, with a range of nearly $1.4 million between a poor outcome and a good one. The ground lease is positive in every case and its range is a third as wide, because the tenant carries cost and leasing. The ground lease is worth more than building in 80 percent of cases.
Revenue outside the buildings
The analysis counts hangar rent only. A new tenant also changes two other lines of the Authority's income. An aircraft that moves to the airport buys fuel here, and the Authority collects the flowage fee of $0.12 per gallon. An aircraft that moves from a tiedown into a hangar stops paying tiedown rent of $85 per month. From the Authority's flowage records, a based piston single uplifts about 610 gallons a year and a based turbine aircraft about 21,400.
| Effect | First year | Present value over 40 years |
|---|---|---|
| Flowage from four piston aircraft new to the airport, T-hangars | $293 | $5,947 |
| Tiedown rent given up by six tenants that move, T-hangars | ($6,120) | ($124,295) |
| Flowage from two turbine aircraft new to the airport, box hangars | $5,136 | $104,310 |
Exhibit 29. Income outside the buildings that the financial analysis leaves out. The split between new and existing tenants follows the survey. Illustrative figures for a sample airport.
Counting these lines would lower the T-hangar result by about $118,000, unless the tiedowns are let again, and raise the box hangar result by about $104,000. Neither changes a finding. They point the same way the findings do: the box hangars bring new aircraft and new fuel sales, and the T-hangars mostly move tenants the Authority already has.
9. Build or Ground Lease
The Authority does not have to build the box hangars to benefit from them. It can lease the four sites to tenants who build their own hangars under the leasing policy. We compared the two on the same 40 year horizon and the same 6.50 percent rate.
Under a ground lease the Authority leases four sites of 8,400 square feet each, 33,600 square feet in all, at the scheduled aeronautical ground rent of $0.45 per square foot. That is $15,120 in the first year, adjusted 2.75 percent a year, for a 30 year term. At expiration the improvements revert to the Authority, which then collects the building rent for the last ten years of the building's life.
| Item | Authority builds | Ground lease to tenants |
|---|---|---|
| Capital required from the Authority | $2,328,704 | $0 |
| Present value of ground rent, years 1 to 30 | Not applicable | $265,642 |
| Present value of building income | $2,692,524, years 1 to 40 | $376,696, years 31 to 40 |
| Net present value to the Authority | $363,820 | $642,337 |
| Who carries construction and leasing risk | The Authority | The tenants |
Exhibit 30. Authority-built and ground lease alternatives for the box hangar sites. Illustrative figures for a sample airport.
The ground lease is worth $642,337 to the Authority and building is worth $363,820. The ground lease also leaves $2,328,704 of capital available for projects no tenant will fund. Building gives the Authority control of the units and all of the income from the first year. On these figures the ground lease is the stronger choice.
The tenant's side of the ground lease
A ground lease has value to the Authority only if tenants will build. We modeled one box hangar from the tenant's side: a cost of $582,176 on an 8,400 square foot site, ground rent at $0.45, and the same expenses and renewal as above. An owner that builds for its own aircraft saves the $12.00 rent it would pay. An investor earns that rent, less 3 percent vacancy. Neither receives anything for the hangar at expiration.
| Lease term | Present value to the Authority, four sites | Owner's return, own aircraft | Investor's return |
|---|---|---|---|
| 25 years | $860,793 | 4.66 percent | 4.34 percent |
| 30 years | $642,337 | 5.80 percent | 5.52 percent |
| 35 years | $459,727 | 6.50 percent | 6.24 percent |
| 40 years | $307,081 | 6.96 percent | 6.71 percent |
Exhibit 31. The ground lease from both sides, by length of term. Illustrative figures for a sample airport.
Term moves value between the parties. At 30 years the Authority's interest is worth $642,337 and an owner earns 5.80 percent. At 35 years the owner reaches the Authority's own 6.50 percent rate. At 40 years the Authority receives ground rent only within the life of the building, $307,081, which is less than the $363,820 it would earn by building.
Two conclusions follow. At the 30 year term the leasing policy sets for this investment, the ground lease is the stronger choice for the Authority. Each five year option the Board later grants defers the reversion and has a price: the first costs the Authority $182,610 in present value and the second $152,646. And the tenant's return at 30 years is modest. Owners build hangars for reasons beyond return, and no box hangar is available to rent at any price while 31 names wait for six units. The margin is thin enough that the Authority should test interest before it relies on the ground lease. Section 11 makes that the first step.
When building is worth more
The comparison depends on the rate. At 6.50 percent the ground lease is worth $278,517 more than building. The two are equal at 5.46 percent. If the Authority can fund the hangars at a cost below that rate, and is willing to carry construction and leasing risk, building is worth more.
Who carries what
| Risk | Authority builds | Ground lease |
|---|---|---|
| Construction cost | Authority | Tenant |
| Lease-up and vacancy | Authority | Tenant |
| Maintenance and capital renewal | Authority | Tenant, during the term |
| Market rent for the buildings | Authority, from year 1 | Authority, after reversion |
| Whether anyone builds | None | Authority. The sites earn nothing until a tenant commits |
| Condition of the hangars at year 30 | Authority controls it | Depends on the surrender terms of the lease |
Exhibit 32. Risk carried under each alternative. Sample provisions.
10. Compliance Notes
- The east hangar area is shown for hangar development on the airport layout plan. Grant Assurance 29 requires development to conform to the approved plan.
- Ground leases for the box hangar sites should follow the Authority's leasing policy on term, rent adjustment, and reversion, and should be offered so that every interested party has the same opportunity. Grant Assurance 22 requires reasonable terms without unjust discrimination.
- New units must be used for aeronautical purposes. Under the FAA's policy on non-aeronautical use of airport hangars, storage of active aircraft is aeronautical use.
- If the T-hangars are built with grant funds, the grant terms and Grant Assurance 24 govern how the federal share enters the rate base.
These notes identify the federal provisions that bear on the decision. They are not legal advice.
Rules on funding a hangar
| Rule | Source | Effect on this project |
|---|---|---|
| A hangar is a revenue producing aeronautical support facility | 49 U.S.C. 47102(24) | Eligible for federal funds only on the terms below |
| The federal share comes only from nonprimary entitlement funds, at a nonprimary airport | 49 U.S.C. 47110(h) | Wexley Field is a nonprimary airport. Discretionary funds are not available for the buildings |
| The sponsor must have provided for the airside needs of the airport | 49 U.S.C. 47110(h) | The Authority shows that airfield needs for the current and next two fiscal years are funded before it applies |
| The entitlement is $150,000 a year and may be banked for up to four years | 49 U.S.C. 47114(d)(2)(A) and 47117(b)(1) | About $600,000, which is 35.5 percent of the T-hangar cost |
| A 95 percent federal share applied to nonhub and nonprimary airports in fiscal years 2025 and 2026 | 49 U.S.C. 47109(h) | The Authority confirms the share in force for the year of the grant |
| Airport Infrastructure Grants do not carry the conditions in section 47110(h) | Public Law 117-58. Allocated for fiscal years 2022 through 2026 and available until September 30, 2030 | Any allocation the Authority has not spent may be applied to a hangar |
| Where an aircraft owner builds a hangar at its own expense, the sponsor grants a long-term lease | Grant Assurance 38 and 49 U.S.C. 47107(a)(21) | Supports the ground lease of the box hangar sites |
Exhibit 33. Federal rules on funding a hangar and what each means here. Summaries, not legal advice.
Terms the leasing policy sets for the box hangar sites
| Term | Leasing policy | Applied to a box hangar site |
|---|---|---|
| Initial term | By investment per square foot of the area developed, clause 8.1 | $69.31 per square foot meets the $50 tier: up to 30 years |
| Options | Up to two of five years, each with Board consent, clause 8.2 | Each defers the reversion valued in Section 9 |
| Ground rent | Schedule rate, clause 9.1 | $0.45 per square foot, $3,780 a year for each site |
| Adjustment | Index each year and a reset every fifth year, Section 10 | Modeled here at 2.75 percent a year |
| Title | Passes to the Authority at expiration, clause 11.3 | Building rent to the Authority from year 31 |
| Cost certification | Within 120 days after completion, clause 8.6 | Confirms the tier on which the term was set |
| Use | Aeronautical, clause 14.3 | Storage of active aircraft and the other uses the FAA policy lists |
Exhibit 34. How the Authority's leasing policy applies to a ground lease of a box hangar site. Sample provisions.
Clause references are to the Authority's Leasing Policy and Rents and Fees Policy.
11. Findings and Recommendation
- Demand exists for both products at market rent: 17 qualified names for ten T-hangars and 7 for four box hangars.
- Market rent for new units is $450 per month for a T-hangar and $12.00 per square foot per year for a box hangar.
- The box hangars are feasible, with a net present value of $363,820 if the Authority builds them.
- Offering the box hangar sites by ground lease is worth more to the Authority, $642,337, and requires no capital.
- The T-hangar building is not feasible on rent alone. It should proceed only if grants cover at least 54.3 percent of its cost.
Implementation
| Step | What the Authority does | Decision it supports |
|---|---|---|
| 1 | Asks the seven box hangar names, and the public, whether they would build on a 30 year ground lease at the Schedule rent | Whether tenants will build |
| 2 | If four qualified parties commit, offers the four sites under the leasing policy | Ground lease, as recommended |
| 3 | If fewer commit, builds the remaining hangars itself, where bids are within 15.1 percent of the estimate | The fallback: building is feasible |
| 4 | Banks its entitlement and asks the state about hangar loan or grant funds | Whether the T-hangar gap can be closed |
| 5 | Takes signed agreements with deposits for the T-hangar units at $450 | Whether the demand is real |
| 6 | Returns to the Board with funding and commitments in hand | Whether to build the T-hangars |
Exhibit 35. Implementation steps. Sample provisions.
Decision gates for the T-hangars
- Funding. Grants, or the value of a subsidized loan, cover at least 54.3 percent of cost, $917,042.
- Commitments. Signed agreements with deposits are in hand for at least seven of the ten units at $450 per month.
- Cost. Bids confirm the estimate. Each 10 percent of added cost adds about $169,000 to the gap.
- Airside needs. The Authority can show that airfield needs for the current and next two fiscal years are funded.
What to watch
- The lists. The count on each waiting list, published each quarter under the leasing policy. A falling box hangar list after Halverson's hangars open would weaken the case.
- Construction cost. The estimate is in current dollars. It should be refreshed if a contract is not awarded within a year.
- Rent at the competing airports. The concluded rents rest on four airports. A change at Corbin or Halverson moves the range.
12. About Valuation Takes Flight
Valuation Takes Flight LLC is an aviation valuation and advisory firm. Dr. Clay W. Carter, DBA, CFA, FRM, CAIA, CIPM, founded the firm and leads every engagement. He is the author of Valuing Aircraft Hangars: A Textbook for Real Estate Appraisers, and the firm publishes the GA Hangar Rent Index, a quarterly market-rent benchmark for US general aviation hangar storage.
The firm prepares hangar feasibility and demand studies, hangar rent studies, rates and charges studies, and hangar appraisals for airport sponsors, developers, lenders and owners nationwide. Construction cost in a feasibility study comes from the client's engineer or builder.
Addendum A. Assumptions and Limiting Conditions
- This is a study of demand, rent and financial return. It is not an appraisal, an engineering report or a legal opinion.
- Construction cost was supplied by the Authority's engineer. We used it as given and did not verify it.
- Based aircraft counts, the waiting lists, flowage records and rent schedules were supplied by airport management and are assumed to be accurate.
- Rents at the competing airports were confirmed with each sponsor or operator as of the date of the study.
- The waiting list survey records what each respondent said it would do. A statement of intent is not a commitment, and Section 4 tests the difference.
- Projections are estimates of future income and expense under stated assumptions. Actual results will differ.
- The analysis is before any tax, and assumes the Authority pays no property or income tax on its own buildings.
- We did not study environmental conditions, airspace, drainage or utility capacity. The study assumes the east hangar area can be developed as shown on the airport layout plan.
- Grant and loan funding is described from published federal law and policy as of the date of the study. Eligibility is determined by the funding agency.
- The study is for the use of the Board of Commissioners in deciding on the east hangar area. It should not be relied on by others or for another purpose.
Addendum B. Terms Used
| Term | Meaning in this study |
|---|---|
| Box hangar | A free-standing rectangular hangar for one tenant. The units studied are 60 by 60 feet |
| Capital renewal | A periodic outlay to replace building components such as doors and roofing |
| Effective gross income | Rent at full occupancy less vacancy and collection loss |
| Entitlement | Federal funds apportioned to an airport each year by formula |
| Ground lease | A lease of land on which the tenant builds. The improvements pass to the Authority when it ends |
| Internal rate of return | The discount rate at which the present value of a project's cash flow equals its cost |
| Net operating income | Effective gross income less operating expenses and reserves |
| Net present value | The present value of a project's cash flow less its cost. A positive figure means the project earns more than the discount rate |
| Nonprimary airport | An airport that is not a primary commercial service airport. Most general aviation airports are nonprimary |
| Return on cost | Stabilized net operating income divided by development cost |
| Reversion | The passing of a tenant's improvements to the Authority at the end of a ground lease |
| T-hangar | A building of nested T-shaped units, each sized for one light aircraft |
Addendum C. Authorities and Sources
Statutory and policy references are summarized by the firm and are not legal advice.
- 49 U.S.C. 47102(24), 47107(a)(21), 47109(h), 47110(h), 47114(d)(2)(A) and 47117(b)(1). Discussed in the firm's paper on federal hangar funding.
- Infrastructure Investment and Jobs Act, Public Law 117-58, division J, title VIII (Airport Infrastructure Grants).
- Federal Aviation Administration. Airport Sponsor Assurances (April 2025): Assurances 22, 24, 29 and 38. faa.gov
- Federal Aviation Administration. Order 5190.6C, Airport Compliance Manual, effective February 20, 2026, paragraph 17.9. See what Order 5190.6C changes.
- Federal Aviation Administration. Policy on the Non-Aeronautical Use of Airport Hangars, 81 Fed. Reg. 38906 (June 15, 2016). Summarized at the hangar use policy.
- Wexley Field Airport Authority. Leasing Policy and Rents and Fees Policy, effective July 1, 2026. A sample document.
- Turner Building Cost Index, annual changes 2022 through 2025, and the Minnesota Department of Transportation hangar loan program, as reported in the firm's papers on hangar waiting lists and FAA rate policy and federal hangar funding.